SAP Sales and Distribution Certification Practice Exam

Disable ads (and more) with a membership for a one time $4.99 payment

Prepare for the SAP Sales and Distribution Certification Exam. Study with flashcards and multiple-choice questions, each offering hints and explanations. Get exam ready today!

Practice this question and more.


What date is crucial for conducting the availability check (ATP)?

  1. Request delivery date

  2. Replenished lead date

  3. Material availability date

  4. Goods issue date

The correct answer is: Material availability date

The material availability date is a critical factor when conducting an availability check, also known as Available To Promise (ATP). This date is essential because it represents the point at which the material is expected to be available for sale and can be allocated to a customer order. The availability check assesses whether the requested quantity of material can be provided by this date, thus ensuring that customer commitments can be met without delay. In the context of SAP Sales and Distribution, this check plays a pivotal role in inventory management and planning processes, enabling businesses to make informed decisions regarding order fulfillment. If the material is not available by the material availability date, it can lead to stock-outs and unmet customer demands, which ultimately affects customer satisfaction and business reputation. Other dates mentioned, such as the request delivery date and goods issue date, are also relevant to the fulfillment process but do not directly determine the availability of materials. The replenished lead date pertains more to replenishment strategies rather than ATP checks. Each of these other dates has its significance in related processes but does not serve the same role as the material availability date in ensuring that stock is ready for orders on time.